采用时序InSAR技术监测北京地铁网络沿线地面沉降
祝秀星, 陈蜜, 宫辉力, 李小娟, 余洁, 朱琳, 周玉营, 李昱

The Subsidence Monitoring along Beijing Subway Network Based on MT-InSAR
ZHU Xiuxing,CHEN Mi,GONG Huili,LI Xiaojuan,YU Jie,ZHU Lin,ZHOU Yuying,LI Yu
表2 沉降槽统计分析结果
Tab. 2 Statistical analysis results of sedimentation trough
时间 Smax/mm i/m
2010-11-19 -4.46 42.93
2011-06-27 -7.58 67.90
2011-12-20 -14.28 134.70
2012-06-02 -16.65 137.80
2012-11-14 -18.02 146.50
2013-05-31 -22.93 147.45
2013-12-26 -27.53 167.55
2014-06-09 -29.79 160.85
2014-12-13 -35.25 167.75
2015-06-29 -36.01 172.85
2015-12-11 -47.39 173.60
2016-11-16 -41.82 179.80